We have mowers working on the "Rails to Trails" pathway from Tenino to Yelm. Please give the operator plenty of room to maneuver, and keep children and pets a safe distance from the mower deck.
Starting on Monday, there is a three-day paving project at the Waste and Recovery Center on Hogum Bay Rd (formerly known as the Landfill).
On Bald Hill Rd SE, from Smith Prairie Rd. to Peissner Rd. the crews will be spending four days paving if the weather allows.
On Wright Rd SE, they are finishing up that project with some final culvert work and paving. That is scheduled for three days.
The sweepers are working in the NPDES areas.
Please remember, don't sweep your leaves into the streets, and take a moment to uncover storm drains near your home if you see leaves piling up on them.